 June 24, 2009
Drilling update on north ayzar number 1 well

 Set 95/8" casing at 411 meter and drilling ahead in 8.5" hole at 530 meter, to hydrocarbon objectives between 1700 and ptd 1950 meter. Wireline evaluation will occur at td. In event hydrocarbon anomalies are encountered in this well, the well will be cased and suspended for subsequent testing with workover rig.
 
 